1.
IMG > MM > IM > goods receipt > Set "Delivery Completed" Indicator.
Here you can set if "Delivery Completed" Indicator shall be
defaulted for your plant if the receipt is withing the
over-/underdelivery tolerances.
Which are either maintained manually in PO or coming via purchasing value key and material
Which are either maintained manually in PO or coming via purchasing value key and material
2.
If you manually activate the indicator in PO it will be closed only from the MRP perspective and still will allow you to make goods receipt . (I doubt this point, I need to test it !!!)
If you manually activate the indicator in PO it will be closed only from the MRP perspective and still will allow you to make goods receipt . (I doubt this point, I need to test it !!!)
3.
you can use mass maintenance for PO with program MEMASSPO(not found in 4.6C...) and choose delivery completed
Maybe the only useful information is item 1.